Elevated Rotaries

Elevated rotaries were constructed at MAO College and at Jain Mander station.Between these rotaries largest and widest station of Metro Bus System was constructed. These were the cast insitu heavy structures of the package III of Metro bus system. In this structure Box girder are used. Each was carrying the concrete 3370m3 and steel 1900 ton and 1730m3 & steel 720 ton respectively. Approximately 800 manpower were involved for construction these rotaries.

With providing comprehensive Project Management, using new methodology and techniques, Reliable was able to complete these rotaries in a record short span of time of 83 days in the history of Pakistan.

 

 

.

.